Air Force Village West


Project Name: Design-Built of Cooling Tower Emergency Replacements and Upgrades

Category: Real Estate Development

Discipline: Mechanical, Electrical, Plumbing, Structural and Construction

PM: Tim Pham

Client: Air Force Village West


Air Force Village West: Design-Built of Cooling Tower Emergnecy Replacements and Upgrades


Scope of Work :

Project Overview

  • A design-built project to replace and upgrade an undersized central plant for the Air Force Village West including Skill Nursing and Special Care Facilities, Assisted Living Buildings, and Kitchen & Dining.

Scope of Work

  • Installation of two coolingAir Force Village Replacement
    towers for redundancy and
    backup, and electrical
    supports for mechanical
    upgrades.

  • Electrical systems were
    designed for connection to
    the existing emergency
    distribution board and
    emergency generators.

  • New controls with variable
    frequency drive VFD were
    installed for cost effective
    and energy savings.

  • Performed a study and
    evaluation of the existing
    two pipe chilled/hot water
    systems for the entire complex. In the report, DTA carefully analyzed the causes and effects of building pressures, weather effects, diversity occupancies’ effects, and system cooling/heating load calculations.

  • Worked closely with building engineers and building operators to provide several alternative solutions. Budgets were developed for each approach.

  • Provided a complete project management through the construction phase, and worked closely with the contractors to maintain the phased schedule.